On Sun, May 10, 2015 at 12:11:49AM +0530, Vijay Bellur wrote:
> On 05/09/2015 12:45 AM, Vijay Bellur wrote:
> >Hi All,
> >
> >Thanks to all our efforts, we are inching closer towards 3.7.0. Here is
> >the updated release schedule for 3.7.0:
> >
> >1. Patch merge deadline and beta2 tagging - 1600 UTC 05/09
> >
> >2. Final test window starts at 1600 UTC 05/09
> >
>
> Update: We are pushing out patch merge deadline and start of final test
> window to 0630 UTC on 05/10.
>
> A few backports which are good to be in 3.7.0 landed late and we faced
> issues with failing regression tests. Hence the postponement.
>
> We have gone ahead and marked all known regression failures as bad tests. So
> a failure from one of these tests will not affect regression runs anymore
> and this should help us in merging code faster. These tests are the ones
> that would need to be picked up by us asap and fixed so as to unblock
> merging of other patches in the affected components.
>
> This is the final deadline extension for 3.7.0 and anything beyond 0630 UTC
> on 05/10 will be part of 3.7.1.
The v3.7.0beta2 tag has been pushed. We expect that beta-2 will become
the actual 3.7.0 release. Some more testing will be done, and hopefully
we can release 3.7.0 in the next few days.
Thanks,
Niels
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: application/pgp-signature
Size: 181 bytes
Desc: not available
URL: <http://www.gluster.org/pipermail/gluster-devel/attachments/20150510/11bbf268/attachment.sig>
More information about the Gluster-devel
mailing list