[Gluster-Maintainers] Release 7: Kick off!
Rinku Kothiya
rkothiya at redhat.com
Tue May 7 10:56:12 UTC 2019
It is time to start some activities for release-7.
## Scope
It is time to collect and determine scope for the release, so as usual,
please send in features/enhancements that you are working towards
reaching maturity for this release to the devel list, and mark/open the
github issue with the required milestone [1].
## Schedule
Curretnly the plan working backwards on the schedule, here's what we have:
- Announcement: Week of Aug 4th, 2019
- GA tagging: Aug-02-2019
- RC1: On demand before GA
- RC0: July-03-2019
- Late features cut-off: Week of June-24th, 2018
- Branching (feature cutoff date): June-17-2018
(~45 days prior to branching)
- Feature/scope proposal for the release (end date): May-22-2018
Regards
Rinku Kothiya
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.gluster.org/pipermail/maintainers/attachments/20190507/a6c9acb3/attachment.html>
More information about the maintainers
mailing list