On 05/31/2018 09:22 AM, Shyam Ranganathan wrote:
> As brick-mux tests were failing (and still are on master), this was
> holding up the release activity.
> 
> We now have a final fix [1] for the problem, and the situation has
> improved over a series of fixes and reverts on the 4.1 branch as well.
> 
> So we hope to branch RC0 today, and give a week for package and upgrade
> testing, before getting to GA. The revised calendar stands as follows,
> 
> - RC0 Tagging: 31st May, 2018

RC0 Tagged and off to packaging!

> - RC0 Builds: 1st June, 2018
> - June 4th-8th: RC0 testing
> - June 8th: GA readiness callout
> - June 11th: GA tagging
> - +2-4 days release announcement
> 
> Thanks,
> Shyam
> 
> [1] Last fix for mux (and non-mux related):
> https://review.gluster.org/#/c/20109/1
> 
> On 05/09/2018 03:41 PM, Shyam Ranganathan wrote:
>> Here is the current release activity calendar,
>>
>> - RC0 tagging: May 14th
>> - RC0 builds: May 15th
>> - May 15th - 25th
>>   - Upgrade testing
>>   - General testing and feedback period
>> - (on need basis) RC1 build: May 26th
>> - GA readiness call out: May, 28th
>> - GA tagging: May, 30th
>> - +2-4 days release announcement
>>
>> Thanks,
>> Shyam
>>
>> On 05/06/2018 09:20 AM, Shyam Ranganathan wrote:
>>> Hi,
>>>
>>> Release 4.1 has been branched, as it was done later than anticipated the
>>> calendar of tasks below would be reworked accordingly this week and
>>> posted to the lists.
>>>
>>> Thanks,
>>> Shyam
>>>
>>> On 03/27/2018 02:59 PM, Shyam Ranganathan wrote:
>>>> Hi,
>>>>
>>>> As we have completed potential scope for 4.1 release (reflected here [1]
>>>> and also here [2]), it's time to talk about the schedule.
>>>>
>>>> - Branching date (and hence feature exception date): Apr 16th
>>>> - Week of Apr 16th release notes updated for all features in the release
>>>> - RC0 tagging: Apr 23rd
>>>> - Week of Apr 23rd, upgrade and other testing
>>>> - RCNext: May 7th (if critical failures, or exception features arrive late)
>>>> - RCNext: May 21st
>>>> - Week of May 21st, final upgrade and testing
>>>> - GA readiness call out: May, 28th
>>>> - GA tagging: May, 30th
>>>> - +2-4 days release announcement
>>>>
>>>> and, review focus. As in older releases, I am starring reviews that are
>>>> submitted against features, this should help if you are looking to help
>>>> accelerate feature commits for the release (IOW, this list is the watch
>>>> list for reviews). This can be found handy here [3].
>>>>
>>>> So, branching is in about 4 weeks!
>>>>
>>>> Thanks,
>>>> Shyam
>>>>
>>>> [1] Issues marked against release 4.1:
>>>> https://github.com/gluster/glusterfs/milestone/5
>>>>
>>>> [2] github project lane for 4.1:
>>>> https://github.com/gluster/glusterfs/projects/1#column-1075416
>>>>
>>>> [3] Review focus dashboard:
>>>> https://review.gluster.org/#/q/starredby:srangana%2540redhat.com
>>>> _______________________________________________
>>>> maintainers mailing list
>>>> maintainers at gluster.org
>>>> http://lists.gluster.org/mailman/listinfo/maintainers
>>>>
>>> _______________________________________________
>>> maintainers mailing list
>>> maintainers at gluster.org
>>> http://lists.gluster.org/mailman/listinfo/maintainers
>>>
>> _______________________________________________
>> Gluster-devel mailing list
>> Gluster-devel at gluster.org
>> http://lists.gluster.org/mailman/listinfo/gluster-devel
>>
> _______________________________________________
> Gluster-devel mailing list
> Gluster-devel at gluster.org
> http://lists.gluster.org/mailman/listinfo/gluster-devel
> 


More information about the maintainers mailing list