[Gluster-infra] Opinions on ideal time for gerrit downtime

Nigel Babu nigelb at redhat.com
Thu May 26 03:50:58 UTC 2016


Thanks Vijay,

I'm leaning towards the morning slot, so it's done before everyone starts
work.

On Thu, May 26, 2016 at 8:20 AM, Vijay Bellur <vbellur at redhat.com> wrote:

> On 05/25/2016 07:02 AM, Nigel Babu wrote:
>
>> Hello folks,
>>
>> I'd like to bring down gerrit for 2 hours some time next week to migrate
>> our database from H2 to PostgreSQL. This will start us on the path to
>> scaling gerrit better. This migration will also speed up the process of
>> upgrading gerrit to the latest version and having our install running
>> newer releases of gerrit quickly.
>>
>> There is really no good time to bring down an essential service like
>> gerrit. My proposal is Monday 0230[1] UTC or 1230[2] UTC. I've looked at
>> our git punchcards and it's a reasonably quiet time to bring down gerrit
>> for maintenance.
>>
>
> Thank you for taking up this much needed change! Both time slots look good
> to me.
>
>
>> In the meanwhile, I'd appreciate some feedback on review.nigelb.me
>> <http://review.nigelb.me> which is a snapshot of our gerrit instance
>> from this morning but with the database powered by postgres. I'd
>> appreciate feedback that the permissions work as expected and reviewing
>> works as expected. This instance does not replicate to github, so feel
>> free to push commits to test.
>>
>
> Did not notice anything with my limited testing on this gerrit instance.
> Everything I tried seems to be working as expected.
>
> -Vijay
>
>


-- 
nigelb
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://www.gluster.org/pipermail/gluster-infra/attachments/20160526/bb274ac1/attachment.html>


More information about the Gluster-infra mailing list