[Gluster-infra] Migrating Gerrit and Jenkins out of iWeb

Amye Scavarda amye at redhat.com
Wed Feb 17 01:39:20 UTC 2016


On Tue, Feb 16, 2016 at 12:20 PM, Michael Scherer <mscherer at redhat.com> wrote:
> Le mardi 16 février 2016 à 23:05 +0530, Kaushal M a écrit :
>> On Feb 12, 2016 10:50 PM, "Kaushal M" <kshlmster at gmail.com> wrote:
>> >
>> > On Fri, Feb 12, 2016 at 10:47 PM, Michael Scherer <mscherer at redhat.com>
>> wrote:
>> > > Le vendredi 12 février 2016 à 12:16 +0100, Michael Scherer a écrit :
>> > >> Le mercredi 10 février 2016 à 19:18 +0530, Kaushal M a écrit :
>> > >> > On Wed, Feb 10, 2016 at 1:53 PM, Michael Scherer <mscherer at redhat.com>
>> wrote:
>> > >> > > Le mercredi 10 février 2016 à 11:44 +0530, Kaushal M a écrit :
>> > >> > >> On Sun, Feb 7, 2016 at 2:34 PM, Michael Scherer <
>> mscherer at redhat.com> wrote:
>> > >> > >> > Le samedi 06 février 2016 à 18:17 -0500, Vijay Bellur a écrit :
>> > >> > >> >> I think starting around 0900 UTC on Friday of next week (12th
>> Feb)
>> > >> > >> >> should be possible. We should be done with 3.7.8 before that
>> and can
>> > >> > >> >> afford a bit of downtime then. In case any assistance is
>> needed post the
>> > >> > >> >> migration, we can have folks around the clock to help.
>> > >> > >> >>
>> > >> > >> >> If migration fails for an unforeseen reason, would we be able
>> to
>> > >> > >> >> rollback and maintain status quo?
>> > >> > >> >
>> > >> > >> > Yes. Worst case, I think people would just redo a few reviews
>> or push
>> > >> > >> > again patch.
>> > >> > >> >
>> > >> > >> > Also, since gerrit is critical, I wonder what is the support of
>> gerrit
>> > >> > >> > for slaves and replication.
>> > >> > >>
>> > >> > >> Michael are you okay with the time? If you are, I think we should
>> > >> > >> announce the migration.
>> > >> > >
>> > >> > > I am ok.
>> > >> >
>> > >> > So as discussed in the community meeting, we will be announcing the
>> > >> > migration and downtime. Vijay, you said you required the exact
>> > >> > schedule? This is what I expect
>> > >> >
>> > >> > Friday 12th Feb 2016
>> > >> >
>> > >> > 0900 UTC : build.gluster.org and review.gluster.org are taken down
>> and
>> > >> > migration begins.
>> > >> > <1-2 hrs?>: Michael copies over data onto the RH community infra and
>> > >> > sets up the VMs.
>> > >> > <? hrs>: The DNS records are updated, and some time is for it to
>> propogate.
>> > >> > <3hr?>: Verify everything is working well (I can help with this).
>> We'd
>> > >> > possibly need to run a regression job, so this will take longest I
>> > >> > think.
>> > >> >
>> > >> > 1700UTC <or earlier>: We announce the finish of the migration and
>> open
>> > >> > the services back up. If migration failed, we bring the existing
>> > >> > servers back on, and continue on.
>> > >>
>> > >> So, for people wanting to know, the migration has started.
>> > >>
>> > >> 1) gerrit
>> > >> ----------
>> > >> gerrit seems to be ok, it has a new IP 66.187.224.201
>> > >>
>> > >> people who used to have access there need to contact me so I can
>> > >> explain/create required account on the new virt host.
>> > >>
>> > >> the old VM is shutdown for now. I will make a backup copy of the disk.
>> > >>
>> > >> 2) jenkins
>> > >> ----------
>> > >>
>> > >> so the preparation of the migration didn't worked as well, so we have
>> to
>> > >> copy the VM when offline, and then prepare it later ( ie, import in
>> > >> libvirt, adjust network, etc). So jenkins master is offline (sorry manu
>> > >> for your tcpdump monitoring), we are making a copy of the disk that is
>> > >> gonna take between 3 and 14h (most likely < 4h, but rsync estimation is
>> > >> moving a lot), and then restart like before.
>> > >
>> > > So turn out I was wrong, and the copy is taking a much longer time.
>> > > Despites me trying to investigate why, it didn't copied everything.
>> > >
>> > > So the new plan is to stop the VM, make a local copy of the disk, start
>> > > the VM, and then copy that one over the new server, prepare for the new
>> > > host (firewall, public ip, etc), and sync from the old VM to the new
>> > > host.
>> > >
>> > > All is ok with this plan ?
>> >
>> > Sounds good to me. No need to wait for the copy to happen and the
>> > downtime should be minimal like with gerrit.
>> >
>>
>> Can we schedule this minimal downtime sometime tomorrow? Or if possible
>> tonight itself. Since we don't require a long downtime we can do this
>> anytime we like.
>
> No. I am at ansiblefest/contributor meeting tomorrow and the day after,
> and then I took a PTO on friday, until end of February.

So it sounds like we're going to have to wait until March for this, if
I'm reading this correctly.
Accurate?
- amye

>
>> I'd like to get the migration done by the end of this week (if possible)
>> before Michael goes on vacation.
>
>
> --
> Michael Scherer
> Sysadmin, Community Infrastructure and Platform, OSAS
>
>



-- 
Amye Scavarda | amye at redhat.com | Gluster Community Lead