## Schedule
Curretnly the plan working backwards on the schedule, here's what we have:
- Announcement: Week of Aug 4th, 2019
- GA tagging: Aug-02-2019
- RC1: On demand before GA
- RC0: July-03-2019
- Late features cut-off: Week of June-24th, 2018
- Branching (feature cutoff date): June-17-2018
(~45 days prior to branching)
- Feature/scope proposal for the release (end date): May-22-2018
Regards
Rinku Kothiya
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.gluster.org/pipermail/gluster-devel/attachments/20190507/a6c9acb3/attachment-0001.html>
More information about the Gluster-devel
mailing list