[Gluster-devel] [Gluster-Maintainers] Release Management Process change - proposal
Vijay Bellur
vbellur at redhat.com
Mon May 30 12:43:16 UTC 2016
On Sun, May 29, 2016 at 10:19 PM, Sankarshan Mukhopadhyay
<sankarshan.mukhopadhyay at gmail.com> wrote:
> On Mon, May 30, 2016 at 7:07 AM, Vijay Bellur <vbellur at redhat.com> wrote:
>> Since we do not have any objections to this proposal, let us do the
>> following for 3.7.12:
>>
>> 1. Treat June 1st as the cut-off for patch acceptance in release-3.7.
>> 2. I will tag 3.7.12rc1 on June 2nd.
>> 3. All maintainers to ack content and stability of components by June 9th.
>> 4. Release 3.7.12 around June 9th after we have all acks in place.
>
> Would 3 days be sufficient to get the content for the website and a
> bit of PR written up?
>
Should be ample time for a minor release.
Regards,
Vijay
More information about the Gluster-devel
mailing list